How we ensure high quality: Production of double-glazed windows for energy-efficient windows at Glas Trösch

 5,552

Briefly about EN 1279-6. Product control in production and periodic testing

Glass quality control during the production of glass units Glass Trösch
Photo: Glas Trösch

The EN 1279-6 standard is aimed at guaranteeing the high quality and reliability of insulating glass units used in construction. It is achieved by meeting the regulatory requirements for thermal insulation, sound insulation and other characteristics that ensure its efficient operation. The standard establishes procedures and requirements for the inspection and control of various aspects of insulating glass production, such as:

Requirements for quality control in production: defines the requirements for quality control procedures that the manufacturer must apply during the production of insulating glass units. This includes checking glass properties, airtightness, inter-chamber space and other aspects.

Periodic tests: manufactured insulating glass units are tested to ensure compliance with the requirements. These tests may include measurements of heat transfer, sound insulation, internal and external pressure resistance, etc.

Conformity assessment: the standard specifies procedures that allow manufacturers to assess the conformity of their products with the requirements of the standard and mark it.

This standard is an important tool for ensuring the quality and reliability of insulating glass units used in construction. It helps manufacturers and consumers to ensure that products comply with established norms and can provide effective thermal insulation and other necessary properties for building structures.

Read more about production control on the Glas Troesch sites

Visual inspection of the glass
Photo: Glas Trösch

The main aspects of the quality management system include input, in-process and outcome control.

  1. Input control: All materials for production are tested in a central laboratory in Switzerland. Only materials that have successfully passed the test are used in the plants. Each plant has its own laboratory for incoming inspection.
Today, all Glas Troesch enterprises in Ukraine use energy-efficient and float glass produced at the Euroglas plant in Poland. This plant belongs to the Glas Troesch Group and supplies glass to our production sites throughout Europe (Germany, Poland, Switzerland, France, Ukraine).
  1. In-process control: Visual inspection of parts and materials is carried out at each workstation. There are clearly defined acceptance criteria for each production operation.
Primary and secondary sealant: The quantity and quality of the applied sealant is checked in accordance with regulatory documents. Objective control is carried out to confirm the correctness of the process.
Molecular sieve and water hardness: The moisture absorption capacity of the molecular sieve and the quality of the glass cleaning water are checked daily.
Level of inert gas filling: The gas filling must be at least 90%, and the test is carried out for each line.
Labelling: A quality product must have its own marking to confirm its quality and prevent counterfeiting. That is why all double-glazed windows from Glas Trösch in Ukraine have the appropriate marking on the visible side: GLAS TRÖSCH SWISS TECHNOLOGY.
  1. Output control: The parameters of the finished double-glazed windows are checked in accordance with the standards of Ukraine, and documentation is kept on a daily basis.
Equipment for the production of double-glazed windows at the Glas Troesch plant
Photo: Glas Trösch
Glas Trösch is a key player in the production of energy-efficient double-glazed windows with a focus on high quality. All of our plants have UkrSEPRO certificates of conformity, which confirm compliance with the standards. In addition, the implementation of an advanced quality management system at all of our plants confirms our commitment to high standards. Compliance with the European standard EN 1279-6:2018 ensures important quality control and regular testing during the production of double-glazed windows, ensuring compliance with the requirements for efficiency, thermal insulation and other characteristics of building structures.
The article is published as an advertisement
The views and opinions expressed in this article are those of the authors and do not necessarily reflect the official policy or position OKNA.ua
Find all your architectural solutions through OKNA.ua: Click here to register. Are you a manufacturer and want to establish contact with customers? Click here.